Tuesday, August 12, 2008

MRR2: The forgotten Heroes!

›
S.O.S. Letter to Ministry of Works in 2004 Cadangan Projek Jalan Lingkaran Tengah II – Pakej 11 (MRR2) Conclusion and Recommendation, concer...
3 comments:
Thursday, August 7, 2008

MRR2 FAILURES: Would the TRUTH be told?

›
Yesterday, sun2surf columnist Citizen-Nades in his article "Former minister wins uncivil war" wrote: [quote] The asking price by ...
1 comment:
Wednesday, August 6, 2008

MRR2: Halcrow said the cracks was due to DEF

›
Halcrow's senior consultant (bridge engineering) Roger Buckby said the primary cause of the cracks was the delayed ettringite formation ...
2 comments:

MRR2: Wrong Material used for repair

›
Halcrow senior consultant (bridge engineering) Roger Bucky said he had in 2005 advised PWD not to use carbon fibre straps because the plasti...
1 comment:
Monday, August 4, 2008

MRR2: 3rd repair job to start on 5th Aug 2008

›
Good News! MRR2 has been re-paired! The concrete will not fall anymore and the road is safe for traffic. See - the traffic is flowing down-u...
4 comments:
Sunday, August 3, 2008

MRR2 cracks again - Third Time closure of Flyover!

›
Middle Ring Road II Cracks Again! This is the 3rd time! After repairing it for RM70 million and engaging the German experts on the strengthe...
1 comment:
Wednesday, October 3, 2007

Kajang-Seremban Bridge Beam Collapse

›
The project is Kajang-Seremban Highway (KASEH). The main contractor is IJM Construction Sdn Bhd, a wholly owned subsidiary of IJM Corp Bhd a...
2 comments:
›